Dust. Data. Clarity.

The project is built once. It is recorded five times.

Tellum connects estimating, project management, procurement, project controls and finance so cost, change and margin appear while there is still time to act on them.

SYSTEMS
07 LINKED
LATENCY
04 MIN
OPEN POs
1,284
REGIONS
UK / US
01The problem

One project exists in five different versions.

Each version is maintained by a different person, on a different cycle, in a different system. By the time they agree, the money is already spent.

  • ON SITE

    The foreman knows the riser is three days behind because the valves have not landed.

  • PROJECT SOFTWARE

    The programme still shows the riser starting on Monday. Nobody has updated it.

  • THE ERP

    The purchase order is committed. The revised delivery date was never written back.

  • SPREADSHEETS

    The cost report carries last month's forecast and a labour rate from the tender.

  • THE BOARD REPORT

    Margin is reported at 7.4%. The site knows it is not 7.4% any more.

02The model

Objects, states and owners — held in one connected record.

PROJECTIN PROGRESSPROJECT MANAGERPURCHASE ORDERPO 48127PROCUREMENTSUPPLIER ACKAWAITINGSUPPLIERCOST TO COMPLETERECALCULATEDQUANTITY SURVEYORAPPLICATION FOR PAYMENTAFP 09COMMERCIAL

When the supplier acknowledgement moves, the cost to complete moves, and the application for payment moves with it. The same event, once, everywhere it matters.

03What we do
01

Choose the right tools

We assess what estimating, project management, procurement and finance actually need to do, then keep the systems that earn their place and retire the ones that only create re-keying.

02

Integrate and report

We move committed cost, valuations, change orders and progress between systems on a schedule, so the cost report is produced from records rather than rebuilt by hand each month.

03

Automate the operation

Purchase order approvals, subcontractor payment applications, retention releases and site returns run as tracked steps with an owner and a due date on each one.

04

Move rigid ERP workflows into a flexible operating layer

The ERP stays the ledger. Everything that changes weekly — rates, forecasts, allowances, sequencing — moves to a layer your commercial team can change without a change request.

A cost overrun found in the month-end report is history. Found on the day the supplier slips, it is still a decision.

04An exception
Late supplier confirmationRAISED 2026-07-02
OBJECT
PO 48127 — MECHANICAL VALVES
SUPPLIER
HARLAND PIPEWORK LTD
OWNER
R. OKONKWO — PROCUREMENT
ORDERED
2026-06-11
ACK DUE
2026-06-18
ACK RECEIVED
NONE — 14 DAYS OPEN
Financial consequence

Valve delivery moves to week 34. Riser installation slips six working days. Two mechanical gangs stand idle at £4,180 per day, and AFP 09 loses £62,400 of planned valuation, which moves the cash into the following month.

Tellum raises this on day one of the delay, to the person who can chase it, not at month end.

Project team in hi-vis reviewing drawings in an unfinished concrete building
Dust. Data. Clarity.

Tell us the report that is always late. We will show you where it is held up.

We work with construction contractors in the UK and US. First conversation is a review of your systems and one process, with a written finding at the end.